Click an image to see an enlarged version.

May 8. West side of church, showing metal studs for outside walls and insulation going up. |

May 9 . Apse area facing Mill Creek Parkway.
|

May 8. East side of church. Workers on the lift are finishing the metal studs for exterior wall.
|

May 8. Blessed Sacrament chapel is taking shape.
|
|
|

May 29 - Office area (shown here) and family room are ready for concrete to be poured.
|

May 29 - Roof is starting to go up on higher areas. Front of church is shown here.
|

June 12- Office area. Floor has been poured and steel studs for office walls have been installed
|

June 12- Family Room. Floor has been poured and wall studs are starting to be installed.
|

June 12- Some of the gathering space roof has been installed. Still need many days of continuous clear calm weather to complete roof.
|

July 10- The masonry wainscoating around the building is almost complete.
|

July 10- Dry wall is being installed in office area
|

July 10- Roofing continues. Still need several dry calm days
|
| |
|
| |
|
| |
|