Click on a picture to see an enlargement

Page 1 of 3

<    Page 1    2   3 >

Week of June 11 - Erosion Control Installed

June 18 - Foley Construction moves equipment to site

June 19 - Site work begins!

July 18 - Groundbreaking (click here for more images of groundbreaking)

Sept. 24 - Installation of Underground Utilities begins, starting with Water.

Sept. 28 Water pipes are being lain. Large pipe is for fire protection water, smaller one for "domestic" water.

Week of Oct. 8- Installation of rock and gravel base   for parking lot and roads

 View of drop off area on east side of chiurch

October 23 - Digging the foundation trench.



October 23 - preparing the reinforcing steel for the foundation.

October 25 - ready for concrete

October 25 - the first pour!  Concrete is being poured into the trench to form the foundation of our church.

Bolts are set in the concrete awaiting the structural steel.


Nov. 12 - Trucks containing building steel waiting to be unloaded.

Nov. 12 - Unloading steel.

 